Client: İstanbul Metropolitan Municipality
Name of Project: Avcılar Main Collector Connection
Location: Avcılar / İSTANBUL / TÜRKİYE
Completed Date: 2012, January 12
Scope of Works: Mechanical Installation Waste Water Connection, Pipeling Ø800 – 2600 mm Pipe, Pipeling Ø300-600 mm Insulated Pipe
The Amount of Workdone:
Connection Avcılar Collector to Marmara Main Collector
Excavation: 96.700 m³
Sheet Pile (Palplanj): 45.500 m²
Filling: 27.400 m³
Pipelining Pipe (Ø800-2600): 3.500 mt
Pipelining Insulated Pipe (Ø300-600): 6.000 mt