Construction of Europe Side Road and Infrastructure Istanbul - TURKEY

Construction of Europe Side Road and Infrastructure Istanbul - TURKEY

Client: İstanbul Metropolitan Municipality

Name of Project: Construction for Europe Side Road and Natural Gas – PTT Pipelining

Location: İKİTELLİ / İSTANBUL / TÜRKİYE

Completed Date: 2007, June 15

Scope of Works: Excavation, Filling, All Types of Pipelining (Ø300-1000mm), Spreading and Compacting, Ductile Iron Pipelining, Manhole Works, Electrical Works, Natural Gas and PTT Works, Transportation.

The Amount of Workdone:

  • Excavating: 419.000 m³

  • Filling Rock: 118.500 m³

  • Valve (Ø100-250mm): 10 ea

  • Plywood: 33.000 m²

  • Concrete: 33.500 m³

  • Iron Works: 23.000 kg

  • Pipelining (Ø300-1000mm): 12.000 mt

  • Spread and Compress: 130.200 m³

  • Ductile Pipe Pipelining: 4.600 mt

  • Manhole Works: 140 ea

  • Electrical Works: 3.300 mt

  • Natural Gas and PTT Works: 4.200 mt

  • Transporting: 985.000 kg