Client: Ankara Metropolitan Municipality, BELKO Ltd. Administration / ANKARA
Name of Project: Production Transportation and Laying of Binder and Wearing Asphalt Course of Various Street and Roads of Ankara (I. Section) / ANKARA / TURKEY
Completed Date: 2002, April 05
Scope of Works:
Laying of Corrosion
Laying of Binder
Laying of Plentmix
Excavating Asphalt with Trimmer Machine
Asphalt Patching: 54,000 Tone
The Amount of Workdone:
Laying of Plent: 577,500 Tone
Laying of Plentmix: 577,500 Tone
Laying of Binder: 577,500 Tone
Laying of Corrosion: 577,500 Tone