Client: İstanbul Metropolitan Municipality
Name of Project: Construction for Anadolu Side River Bed Improvement of Tuzla River 2nd Section
Location: Tuzla / İSTANBUL / TÜRKİYE
Completed Date: 2009, June 05
Scope of Works: Excavation, Filling, Every Kind of Pile, Pipeline, Concrete Pipe, Waste Water
The Amount of Workdone:
Excavating: 257.500 m³
Filling Rock: 118.500 m³
Pile (Ø 800 mm): 1.950 mt
Pipelining (Ø300-Ø600) Concrete: 5.555 mt
Shaft: 78 ea
Concrete: 3.150 m³
Plywood: 49.400 m²
Iron Works: 15.500 kg
Transporting: 565.000 kg